Pre-Development Weekly Progress Tracker — v2.2
Analytics Nest Pvt. Ltd.  ·  PM: Syed Nizam Uddin  ·  Prepared for Sir Saleem  ·  June 18, 2026
🔵 Week 3 In Progress · PRD & Flow Diagrams Being Created · Dev Start: July 14, 2026
77
Total Documents
14
✅ Total Completed
3
🔵 Week 3 In Progress
60
⏳ Weeks 3–6 Remaining
43
P1 Critical Docs
July 14
🚀 Dev Start Date
📖 How to Read This Tracker — Overview for Sir Saleem Click to Expand Overview

How does the document sequence work?

This tracker organizes all 77 pre-development documents into 6 weeks. Each document is placed in the week where it is logically required — not by ID number order. Think of it like building a house: you pour the foundation first, then the walls, then the roof. You cannot reverse the sequence.

The document ID numbers (DOC-60, 61, 62, 63) are simply catalogue reference numbers assigned during planning — they do NOT mean those documents belong in the same week. Each goes where its inputs are ready.

DOC-60 — Project Charter
📅 Week 1 · Completed June 5, 2026
✅ Placed in Week 1 because it is the founding document — it formally authorizes the project. Nothing can begin without this signed document.
DOC-61 — RACI Matrix
📅 Week 1 · Completed June 5, 2026
✅ Placed in Week 1 because it assigns responsibilities to every team member. Without this, the team cannot work efficiently.
DOC-63 — Risk Register
📅 Week 1 · Completed June 5, 2026
✅ Placed in Week 1 because risks must be identified before any major decision is made. Early risk awareness protects the project and the investment.
DOC-62 — Sprint Plan
📅 Week 4 · Begins June 23, 2026
⏳ Placed in Week 4 because a Sprint Plan requires the full feature list (PRD) AND all wireframes to be approved first. Creating it earlier would be guesswork.

Core Principle: Every document is created only when all its inputs exist. This disciplined sequencing is what separates a professional software project from a failed one.

🔄 Progress & Timeline Update (Reported to Sir Saleem on June 13): Project planning and document cataloging commenced on June 4, 2026. Week 1 (June 4–8) focused on setup and planning. Product discovery and core business/architecture decisions (including the recommendation to split the Captain and Customer applications, now updated to support motorcycle riders for the new Parcel Delivery service) were finalized in Week 2 (June 9–13). Week 3 (June 14–20) has been dedicated to mapping complex user journeys and flows for the PRD and Flow Diagrams (DOC-18) for all three services to ensure a bulletproof UX before wireframing. Development start date remains July 14, 2026.
📅 Updated Project Timeline (Click on any week to navigate)
Week 1
June 8–14
COMPLETED
3
Docs Done
🔵
Week 2
June 15–21 · CURRENT
IN PROGRESS
10
Docs In Focus
3
Week 3
June 22–28
UPCOMING
11
Docs Planned
4
Week 4
June 29–July 5
UPCOMING
12
Docs Planned
5
Week 5
July 6–12
UPCOMING
18
Docs Planned
6
Week 6
July 13–19
UPCOMING
16
Docs Planned
🚀
Dev Start
July 20, 2026
Sprint 0
GO!
Development
Week 1 — Completed
Week 01 of 06
Project Initiation & Setup
📅 June 4 (Thursday) – June 8 (Monday), 2026
Why this week? — We established the project framework, finalized the master document catalog of 77 documents, assigned roles, and logged initial project risks.
3
Documents
✅ COMPLETED — Project set up and master document catalog finalized
📁 Project Setup & Governance (DOC-60, 61, 63)
DOC-60
Project Charter
Why here: Formally authorizes the project — the very first official document. No other work can start without this.
Owner: PM — Syed Nizam Uddin
P1✅ Done June 5
DOC-61
RACI Matrix
Why here: Defines who is Responsible for every task. Without this, no one knows their role.
Owner: PM
P1✅ Done June 5
DOC-63
Risk Register
Why here: Risks must be identified EARLY before decisions are made. Finding risks late is expensive.
Owner: PM
P1✅ Done June 5
Week 2 — Completed
Week 02 of 06
Product Discovery & Core Decisions
📅 June 9 (Tuesday) – June 13 (Saturday), 2026
Why this week? — We researched user needs, defined the target audience, framed the Business Requirements (BRD), established the driver earnings model, and finalized the decision to build Driver and Customer apps separately.
10
Documents
✅ COMPLETED — Reported to Sir Saleem on June 13, 2026
📁 Product Discovery (DOC-01 to DOC-08) — Understanding the Problem & Users
DOC-01
Problem Statement
Why here: Defines the exact problem Pickia solves. EVERYONE must agree on this before designing anything.
Owner: PM
P1✅ Done June 10
DOC-03
User Personas (4 personas)
Why here: All UX and feature decisions refer back to these personas. Must exist before design starts.
Owner: PM
P1✅ Done June 11
DOC-04
Jobs To Be Done (JTBD)
Why here: Captures WHY users use Pickia — deeper than features. Essential for UX decisions.
Owner: PM
P1✅ Done June 11
DOC-05
Empathy Map
Why here: Helps team feel what users feel before designing. Prevents tone-deaf UX decisions.
Owner: PM + UX
P2✅ Done June 12
DOC-06
Customer Journey Map
Why here: Maps every touchpoint from problem to loyal user. Guides UX and marketing strategy.
Owner: PM + UX
P1✅ Done June 12
DOC-07
Pain Points & Opportunity Map
Why here: Shows exactly where current solutions fail and how Pickia wins. Great for Sir Saleem's review.
Owner: PM
P2✅ Done June 13
DOC-08
Value Proposition Canvas & Naming Report
Why here: Proves Pickia's features match user needs, and includes naming research for Pakistan & Middle East markets.
Owner: PM
P2✅ Done June 13
📁 Business Requirements & Architecture (DOC-09, DOC-N-A, DOC-N-E)
DOC-09
Business Requirements Document (BRD)
Why here: Defines business goals and KPIs. Must come before detailed feature requirements (PRD).
Owner: PM + CEO
P1✅ Done June 13
DOC-N-A
Driver Earnings Model (10% Commission) ⭐ NEW
Why here: Core business logic (10% commission model). Developers need this before building payment module. Now updated to include motorcycle riders.
Owner: CEO + PM
P1NEW✅ Done June 13
DOC-N-E
App Architecture Split Decision (Captain vs Customer App) ⭐ NEW
Why here: Strategic technical decision to build separate Driver (Captain) and Customer apps, validated against Uber/Careem models. Now updated to support motorcycle riders for the new Parcel Delivery service.
Owner: CTO + PM
P1NEW✅ Done June 13
Week 3 — In Progress · Current Week
Week 03 of 06
Requirements, UX Foundation & Flow Diagrams
📅 June 14 (Sunday) – June 20 (Saturday), 2026
Why these docs now? — Requirements tell developers WHAT to build. Flow diagrams show HOW users move through the app. Information Architecture shows WHERE every screen lives. These 3 things must be done BEFORE wireframes.
11
Documents
🔵 IN PROGRESS — Market Research Finalized · Flow Diagrams & PRD Mapping Underway
📁 Requirements Documents (DOC-10 to DOC-16) — What Does the App Do?
DOC-02
Market Research Report
Why here: Validates market size, competitor analysis, and Pakistan transport behavior. Worked on in Week 2, finalized here.
Owner: PM + COO
P1✅ Done June 16
DOC-10
Product Requirements Document (PRD)
Why here: Full feature list with user stories and acceptance criteria. Currently mapping use cases and customer journeys for all three services (Goods, Family, and Parcel).
Owner: PM
P1🔵 In Progress
DOC-11
Functional Requirements Spec (FRS)
Why here: Detailed behavior of every feature — input, output, what happens. Developers cannot code without this.
Owner: PM + CTO
P1🔵 In Progress
DOC-12
Non-Functional Requirements (NFR)
Why here: Performance, security, and uptime targets. CTO needs this to design the correct architecture.
Owner: CTO
P1⏳ Pending
DOC-13
Feature Priority Matrix (MoSCoW)
Why here: Classifies every feature as Must/Should/Could/Won't. Prevents scope creep during development.
Owner: PM
P1⏳ Pending
DOC-14
Scope Document
Why here: Formal definition of what is IN and OUT of Phase 1. Prevents arguments later.
Owner: PM
P1⏳ Pending
DOC-15
Assumptions & Constraints Log
Why here: Documents what we assume to be true. Tracks constraints (budget, Android-only).
Owner: PM
P2⏳ Pending
DOC-16
Glossary of Terms
Why here: Common language for the whole team. Prevents misunderstandings between PM, developers, and designers (updated with Parcel terms).
Owner: PM
P2⏳ Pending
📁 UX Foundation & Logic (DOC-17, DOC-18, DOC-N-B)
DOC-17
Information Architecture (IA)
Why here: Shows ALL screens and how they connect. Must exist BEFORE wireframes.
Owner: UX + CTO
P1⏳ Pending
DOC-18
User Flow Diagrams — All Major Flows
Why here: Step-by-step visual of every user path (Goods, Family, and Parcel Delivery). Currently being created by team. ← CURRENT WORK IN PROGRESS
Owner: UX + PM
P1🔵 Currently Working
DOC-N-B
Pricing Calculator Logic ⭐ NEW
Why here: Exact fare formula (base fare + per km + floor charge for trucks, and base fare + per km for motorcycle parcels). Backend developers MUST have this before building the booking engine.
Owner: CEO + PM + CTO
P1NEW⏳ Pending
Week 4 — Upcoming
Week 04 of 06
Wireframes + Prototype + UI Design + Architecture
📅 June 23 (Monday) – June 27 (Friday), 2026
Why this order? — Wireframes come AFTER flow diagrams (you need to know the flows before sketching screens). High-fi designs come AFTER wireframes. Architecture comes AFTER you know all the features.
12
Documents
⏳ NOT YET STARTED — Begins June 23, 2026
📌 Why DOC-62 (Sprint Plan) is in THIS week: The Sprint Plan is created here because by Week 4, all requirements AND wireframes will be done. Now the PM and CTO can break down the work into 2-week sprints with confidence. Not before.
📁 UX Design — Visual Screens
DOC-19
Wireframes — Low Fidelity (All screens)
Why here: Simple black & white sketches of every screen — comes AFTER flow diagrams (DOC-18) are approved.
Owner: UX
P1⏳ Pending
DOC-20
Wireframes — Mid Fidelity
Why here: Detailed screens with button names and content — built on top of low-fi wireframes.
Owner: UX
P1⏳ Pending
DOC-21
Clickable Prototype (Figma)
Why here: Interactive mockup for user testing — created from mid-fi wireframes.
Owner: UX
P1⏳ Pending
DOC-22
User Testing Report (5–10 real users)
Why here: Test the prototype with real users BEFORE high-fidelity design — saves expensive redesign time.
Owner: PM + UX
P1⏳ Pending
DOC-23
High Fidelity UI Designs
Why here: Final pixel-perfect designs — created AFTER user testing confirms the wireframes are correct.
Owner: UX
P1⏳ Pending
DOC-24
Design System Document
Why here: Color palette, fonts, and reusable UI components — created alongside hi-fi designs.
Owner: UX + CTO
P1⏳ Pending
📁 Technical Architecture — How Is the System Built?
DOC-30
System Architecture Diagram
Why here: Visual map of all system components — CTO designs this AFTER knowing all features from PRD.
Owner: CTO
P1⏳ Pending
DOC-31
Technical Stack Document
Why here: Final technology decisions (Flutter/React Native, Node.js, AWS etc.) — confirmed after architecture is clear.
Owner: CTO
P1⏳ Pending
📁 Project Management (DOC-62, 66) — Now Ready Because Requirements Are Done
DOC-62
Sprint Plan (Week-by-week dev schedule)
Why here (NOT Week 1): Sprint Plan requires knowing ALL features (from PRD) AND all screens (from wireframes). Only now is it possible to break development into logical sprints.
Owner: PM + CTO
P1⏳ Pending
DOC-66
Definition of Done
Why here: Exact criteria for what "complete" means for each feature — defined before development starts.
Owner: PM + CTO
P1⏳ Pending
DOC-N-C
Onboarding Screen Flow ⭐ NEW
Why here: First-time user experience design — created alongside wireframes so onboarding is part of the app flow.
Owner: UX + PM
P1NEW⏳ Pending
DOC-N-D
Admin Panel Requirements ⭐ NEW
Why here: Defines what the admin dashboard shows — created alongside other requirements so developers know the full scope.
Owner: PM + CTO
P1NEW⏳ Pending
Week 5 — Upcoming
Week 05 of 06
Database, APIs, Process Flowcharts & Technical Diagrams
📅 June 30 (Monday) – July 4 (Saturday), 2026
Why this order? — Database schema can only be designed AFTER the system architecture is confirmed. APIs can only be defined AFTER the database schema is designed. Flowcharts finalize the process logic for developers.
18
Documents
⏳ NOT YET STARTED — Begins June 30, 2026
📁 Technical Deep-Dive (DOC-32 to DOC-41)
DOC-32
Database Schema (ERD)
Owner: CTO + Backend
P1⏳ Pending
DOC-33
API Design Document
Owner: CTO + Backend
P1⏳ Pending
DOC-34
Data Flow Diagram (DFD)
Owner: CTO
P1⏳ Pending
DOC-35
Sequence Diagrams (Critical flows)
Owner: CTO
P1⏳ Pending
DOC-36
State Diagrams (Booking, Driver, Trip)
Owner: CTO
P1⏳ Pending
DOC-37
Third Party Integrations Document
Owner: CTO
P1⏳ Pending
📁 Process Flowcharts (DOC-42 to DOC-53)
DOC-42
Business Process Flow
Owner: PM + COO
P1⏳ Pending
DOC-43
Customer Booking Flow — Goods Transport
Owner: PM + UX
P1⏳ Pending
DOC-44
Customer Booking Flow — Family Transport
Owner: PM + UX
P1⏳ Pending
DOC-45
Driver Onboarding Flow
Owner: PM + COO
P1⏳ Pending
DOC-46
Driver Booking Acceptance Flow
Owner: CTO + PM
P1⏳ Pending
DOC-47
Payment Processing Flow
Owner: CTO
P1⏳ Pending
DOC-48
Cancellation & Refund Flow
Owner: PM + CTO
P1⏳ Pending
DOC-49
Dispute Resolution Flow
Owner: PM + COO
P2⏳ Pending
DOC-52
Pre-Booking Confirmation Flow
Owner: PM + CTO
P2⏳ Pending
DOC-53
Error & Edge Case Flows
Owner: CTO + PM
P2⏳ Pending
DOC-40–41
Performance Benchmarks + Scalability Plan
Owner: CTO
P2⏳ Pending
Week 6 — Upcoming
Week 06 of 06 — FINAL WEEK
Security, Legal, Testing Plans + Final Sign-Off
📅 July 7 (Monday) – July 11 (Friday), 2026
Why last? — Legal documents need a lawyer (takes time). Security architecture is designed after the full technical architecture is done. Testing plans are written after all features are fully defined.
16
Documents
⏳ NOT YET STARTED — Begins July 7, 2026
📁 Security + Infrastructure (DOC-38, 39)
DOC-38
Security Architecture Document
Owner: CTO
P1⏳ Pending
DOC-39
Infrastructure & DevOps Plan (AWS)
Owner: CTO + DevOps
P1⏳ Pending
📁 Testing Plans (DOC-54 to DOC-59)
DOC-54–59
Test Plan, Test Cases, UAT Plan, Bug Matrix, Performance & Security Test Plans
Owner: QA + CTO + PM
P2⏳ Pending
📁 Legal & Operations (DOC-70 to DOC-77) — ⚠️ Start Legal Early!
DOC-70
Driver Terms & Conditions
Owner: Legal + CEO
P1⏳ Pending
DOC-71–72
Driver Onboarding Guide + Driver Training Manual (Urdu)
Owner: COO + UX
P1⏳ Pending
DOC-73–74
Customer Terms & Conditions + Privacy Policy (PECA 2016)
Owner: Legal + CEO + CTO
P1⏳ Pending
DOC-75–76
Pricing Policy + Refund & Cancellation Policy
Owner: CEO + PM
P1⏳ Pending
DOC-64–69
Comm. Plan, Change Mgmt, Release Plan, Rollback Plan, Post-Launch Monitoring
Owner: PM + CTO
P2⏳ Pending
After All 77 Documents Are Approved by Co-Founders
🚀 Sprint 0 — Development Officially Begins
Target Date: July 14, 2026  ·  All 77 documents signed off  ·  Development team onboarded  ·  First sprint commences